Karbala refinery
Also known as:
New refinery being built in Iraq by KRC.
Total project cost of $6B.
Refinery configuration
Refinery configuration
Major process units:
Major process units:
Atmospheric distillation - 150 kbpd
Vacuum distillation - 70 kbpd
FCC - 40 kbpd
C5/C6 Isomerization - 12 kbpd
Reformer - 25 kbpd - Continuous (CCR) unit
Naphtha hydrotreater - 40 kbpd
Kerosene hydrotreater - 20 kbpd
Distillate hydrotreater - 80 kbpd
VGO hydrotreater - 36 kbpd
Oxygenates plant
Location
Location
refinery website
Refinery history
Refinery history
2015 - Construction began
2023 - Full operations expected mid year